Case Study: Compact BOP Handling System
Customer Location: Shipyard in China
Scenario: Customer in China needed a custom BOP Handling System with length & height requirements to meet the following:
- Reduce length of standard unit by 1.3M
- Maintain performance of a standard, original BOP system
- Endure harsh conditions
Solution: Custom Designed BOP Handling System
- Total system length of 2.0 meters instead of 3.3 meters from the standard unit.
- Speed and consumption equal of the standard 150T hoisting system.
- Trolleys can fit beams width of 200 mm up to 356 mm.
- Ex-classification: Ex II 2 GD IIA T3 (X) / Ex II 3 GD IIB T3 (X)
- Designed as per FEM, ABS, DNV, CE, ATEX requirements.
Do you need a fully customized BOP Handling System to meet your compact space requirements? Let Ingersoll Rand customize pulling and lifting equipment for you today.